Debarker Removal and Replacement

  • Client Name: Canfor - Houston
  • Project Name: Debarker Removal and Replacement
  • Location: Houston, BC
  • Sector: Forestry

Scope of Work: Removal of old equipment and installation of new Nicholson A8 Debarker

Duration: 1 month

Highlights:

  • Fabrication and installation of approximately 250,000 lbs of structural steel
  • Fabrication and installation of 700,000 lbs of mechanical log handling equipment
  • Demolition of old debarking line
  • Installation of Nicholson A8 debarker
  • Completion of hydraulic piping
  • Civil and concrete work